DISCUSSION/BACKGROUND:
Due
to its relocation, US 6 in Cedar County should be deleted from the primary road
system and the new description added should be officially included in the
primary road system.
US
6 begins on the Cedar‑Muscatine county line near the City of Wilton and
proceeds northerly and easterly to the Cedar‑Scott County line
approximately two miles north of the City of Durant.
PROPOSAL/ACTION
RECOMMENDATION:
It
is recommended the commission approve deleting the present description of US 6
in Cedar County from the primary road system and approve including the attached
new description of US 6 in the primary road system.
Locate
US 6 and its extensions in
Beginning
on the Cedar‑Muscatine county line at a point approximately 300 feet east
of the SW Corner Section 36‑T79N‑R2W, Cedar County (300 feet east
of the NW Corner Section 1‑T87N‑R2W, Muscatine County); thence in a
northwesterly direction through Sections 36 and 25‑T79N‑R2W to a
point approximately 800 feet north of the SW Corner Section 25‑T79N‑R2W;
thence north following substantially the section line through 25 and 24‑T79N‑R2W
to a point approximately ¼ mile north of the W ¼ Corner said Section 24
(junction Interstate 80 and Iowa 38); thence southeasterly through Section 24‑T79N‑R2W
to a point near the E ¼ Corner Section 24‑T79N‑R2W; thence east
following substantially the center section line through Sections 19, 20, 21,
22, 23 and 24‑T79N‑R1W to a point on the Cedar‑Scott Co. line
approximately 2548 feet north of the SE Corner Section 24‑T79N‑R1W,
Cedar County (SW Corner Section 19‑T79N‑R1E, Scott County).
COMMISSION
ORDER
DIVISION:
Planning & Research
COMMISSION
ORDER NUMBER:
PR-79-272
SUBMITTED
BY: C.I. MacGillivray
MEETING
DATE: 11-2-78
DISCUSSION/BACKGROUND:
Due
to a review of our Primary Road System Records, US 6 in Cedar County should be
deleted and the new description added should be officially included into the
Primary System.
PROPOSAL/ACTION
RECOMMENDATION:
It
is recommended that the old description of US 6 in Cedar County be deleted and
the new description, as referred in the attached detailed description, be included in the Primary Road System effective upon the
adoption of this resolution.
Locate
US 6 and its extension in
Beginning
on the Cedar‑Muscatine County line at a point approximately 400 feet east
of the S ¼ Corner Section 33‑T79N‑R1W, Cedar County (N ¼ Corner
Section 4‑T78N‑R1W, Muscatine County); thence in a northeasterly
and easterly direction along the north side of the Chicago, Rock Island, and
Pacific Railway and substantially parallel thereto through Sections 33, 34, and
35‑T79N‑R1W to the west corporation line of the City of Durant connecting
with an unnamed street.
Durant:
Beginning on the west corporation
line connecting with an unnamed street; thence in an easterly direction to the
Cedar‑Scott County line.
REVISED:
4-28-81
OFFICIAL
DESCRIPTION CHANGE
COUNTY:
Cedar
ROUTE:
US 6
APPROVAL
DATE: 4-14-37
Beginning
on the Cedar‑Muscatine County line, at a point approximately 400 feet
east of the S ¼ Corner Section 33‑T79N‑R1W; Cedar County (N ¼
Corner Section 4‑T78N-R1W, Muscatine County); thence in a northeasterly
and easterly direction along the north side of the Chicago, Rock Island and
Pacific Railway through Section 33, 34, and 35‑T79N‑R1W to the west
corporation line of the town of Durant, connecting with Washington Street.
COUNTY:
Cedar
CITY
OF: Durant